Internal Control Disaster: Fiasco at Heathrow

April 2008

In March 2008, London's Heathrow Airport's new Terminal 5 building went live after a huge and exceptionally well-managed building project. Sadly, thanks to problems with baggage handling, it has been a disaster for BAA, who owns the airport, and British Airways, the sole airline using Terminal 5. What can we learn from this experience?

by Matthew Leitch

In a typical post-implementation meltdown, the high error rates and backlogs that often happen when a process or system is new overwhelm the fledgling control system in place, or nearly in place, to deal with them. This can happen even when people are aware that the initial months can be very challenging. The sequence of events usually goes in the stages described below.

Stage 1: Good Intentions

People on the project responsible for designing and implementing controls around the process or system think widely about what they need to do and write a long list of action items. It may be a good list. They make plans. They know management reporting is needed.

Stage 2: First Cracks Appear

Once the project is underway, it may be that things start to fall behind schedule and some strain is felt. Business analysts and process designers take all the time they are allowed and then a little bit more, leaving the controls team with very little time to respond to what is happening. At the same time, they gradually become aware that they are not as skilled or as productive at controls work as they had imagined.

Stage 3: Rising Panic

As project health continues to decline, stress rises, and people begin to revisit their original intentions and make cuts. It is justified as "focusing" but, in reality, this is a kind of tunnel vision that gets progressively narrower. The controls team goes back to its original list of things to do and asks, "What do we really, really need to do by go-live?"

Systems people begin to regard controls work, and management reporting in particular, as "nice to haves" that they can leave until after going live. Some people can't take the pressure and drop out of the project. Testing gets de-scoped and compressed.

As project health declines, the likelihood of high error rates and backlogs upon implementation increases, so controls development becomes more important and should be boosted. Instead, what usually happens is that it declines with everything else, or more so.

Stage 4: Champagne

It's taken long shifts, working through weekends, and the project is a few weeks late, but it's over. Hooray! Champagne corks are popped, and everyone celebrates. It was a success. We've done it.

Stage 5: Emerging Problems

Initially, there is little or no evidence of things going wrong, but after a short while the first, feint indications of problems under the surface begin to emerge. As they are investigated, more problems come to light, and this eventually reveals a ghastly mess of faulty data, stuck transactions, or lost items. It's too late to revert to backups. Thousands of incorrect cases already exist, and the reason this wasn't visible immediately is that not enough checks were being done. The controls weren't in place. Worse still, now there's a lot of work to do, and the management information and supervisory control system needed to oversee it is not in place. These could have been developed and tested before going live as part of other testing, but that was de-scoped.

Stage 6: Long Recovery

There's nothing to do but to bring in temporary staff to cope with the extra work. It may take months to work through all the mistakes and correct them.

What about Terminal 5?

At this stage, few details have emerged about what went wrong, and some of these details are slightly different from a typical meltdown. So far, what has been reported by journalists and the companies involved includes the following points.

Overall, a terrible period for everyone affected.

What Lessons Might Be Learned?

The most obvious lesson from the Terminal 5 baggage fiasco is that a live trial is still a trial. There's nothing quite like live operation. While conducting a dry run can help a lot, it's not enough on its own.

BA seems to have decided that the results of trials were sufficient to justify starting at 70 percent of capacity on day one, when starting at 10 percent or less seems to have been a more reasonable approach. The background has not been made public but, typically, if you deliver incrementally, it is possible to start delivering earlier than if you try to deliver everything (or nearly everything) on the first day—and much can be learned as a result.

After the live trial, there would still have been uncertainties about the productivity of people involved in baggage handling and the reliability of the systems. These uncertainties should have been recognized, measured, and resolved through progressive increases in live operations.

As I have argued many times in previous IRMI articles, our human tendency is to underestimate uncertainties and, consequently, to do too little about them. Most likely, Terminal 5's baggage handling is another example of this phenomenon.

BA seems to have been taken by surprise by events, as suggested by their sending of an illegal letter to customers and the inability to put extra personnel onto moving baggage as soon as a backlog began to develop on the first morning.

Unusually, there is no evidence at this stage of project health problems, with the exception of reports that baggage handling staff were demoralized and unimpressed by the training. It may be that the baggage system project had problems, but the construction work had gone so well that senior people felt that the magic of their risk management approach would work once again.

Conclusion

While Terminal 5 made headlines due to the large scale of the fiasco, post-implementation meltdown is a common experience with causes that are easy to understand. It is essential to comprehend the high risk involved, to implement incrementally if at all possible, and to boost controls development if project health is ever in doubt.


Further Reading

Intelligent Internal Control and Risk Management, by Matthew Leitch, first published in 2008 by Gower Publications (www.gowerpub.com).


Opinions expressed in Expert Commentary articles are those of the author and are not necessarily held by the author's employer or IRMI. Expert Commentary articles and other IRMI Online content do not purport to provide legal, accounting, or other professional advice or opinion. If such advice is needed, consult with your attorney, accountant, or other qualified adviser.

Home > Free Risk & Insurance Information > Expert Commentary > Risk Management > InternalControl > Internal Control Disaster: Fiasco at Heathrow (April 2008)