Design-Build Teammates—Who Pays Liquidated Damages First?

October 2004

Although design-build is now a "mainstream" construction project delivery system, there remain many challenges in properly allocating the risks arising from this system, particularly among design-build team members. A recent case demonstrates how this issue was handled by two major industry players with the context of liquidated damages.

by Michael Loulakis
Wickwire Gavin, P.C.

Siemens Westinghouse Power Corp. v Dick Corp., et al., 293 F Supp 2d 336 (SD NY 2003), involved a suit between members of a consortium over which a member had responsibility to make the initial payment of liquidated damages to a power plant owner for project delays. The court, after looking carefully at the consortium agreement between the parties, concluded that the construction contractor member of the consortium had the ultimate responsibility to pay the owner, and then to seek reimbursement from the turbine vendor member.

Siemens Westinghouse Power Corporation (SWPC) and Dick Corporation formed a consortium to construct a power plant in Londonderry, New Hampshire, for AES Corporation (AES). The contract called for the payment of liquidated damages of $85,000 per day if the project did not achieve "Provisional Acceptance" by a certain date. When Provisional Acceptance was delayed, AES began assessing liquidated damages. Dick made the initial liquidated damages payments, totaling around $3.6 million. At some point, AES began drawing its liquidated damages from letters of credit posed by SWPC. SWPC ultimately paid AES over $18 million in liquidated damages as a result of project delays.

A dispute arose between SWPC and Dick over who had the initial responsibility to pay AES the liquidated damages. SWPC argued that Dick was obligated to pay AES first, with the ultimate apportionment of such damages between SWPC and Dick to be determined later. Dick contended that it was only required to pay liquidated damages to the extent of Dick's fault. The parties were not able to resolve this conflict, resulting in SWPC filing a lawsuit against Dick, its sureties, and others.

The Consortium Agreement

Section 7.6.2 of the consortium agreement was one key provision relative to this dispute. It stated:

Another key provision to this dispute was Section 6.3.2 of the consortium agreement, which read as follows:

SWPC argued that these provisions called for SWPC to pay liquidated damages to Dick, not the Owner. It also cited provisions of the EPC contract that required the payment to AES of liquidated damages on a monthly basis, and that it would be impossible to calculate SWPC's share of the damages, according to the formula in Section 6.3.2, on a monthly basis. Moreover, Section 6.3.2 capped SWPC's share of the liquidated damages at the "demonstrated impact costs Dick incurs in working around or accelerating its work to overcome the delay caused by Siemens Westinghouse," which was a complex analysis that could not be performed on a monthly basis. SWPC also looked to Exhibit G, which stated that SWPC would only be liable for liquidated damages for delay in delivering certain component parts if, after the late component part is delivered and installed, it is determined the SWPC was the "sole cause" of the project's delay. All of these points meant that Dick had to pay liquidated damages in the first instance.

Dick argued that Sections 7.6.2 and 6.3.2, read together, meant that Dick would only be obligated to pay AES after the damages were properly assessed and SWPC paid its share to Dick. Dick relied on the clause, "Dick will be responsible for payment of any schedule liquidated damages ..." and contended that the future tense implied that Dick will be responsible for payment after SWPC paid its share to Dick. Dick also pointed to 10 separate provisions of the consortium agreement which supported the proposition that each member of the Consortium was responsible for its own acts and omissions.

The court noted that even though the contract did not explicitly state that Dick was to pay the damages "in the first instance," or otherwise state that Dick was to pay those damages "before apportionment," the overall structure and language of the provisions required a finding in favor of SWPC. Since the payment obligations ran from Dick to AES, and separately from SWPC to Dick, the structure suggested that SWPC was to reimburse Dick for its payments to AES. It was also persuaded by the fact that Dick was unable to counter SWPC's observation that the complex apportionment calculations required by Section 6.3.2 could not be performed alongside the monthly payment schedule required under the contracts with the Owner.

The Role of the Sureties

The court also concluded that Dick's sureties were jointly and severally liable to reimburse SWPC for its $18 million payment to AES. The sureties had argued that they could not be liable on Dick's behalf because the surety bonds required, as a condition precedent to payment, that SWPC fulfill all its contractual obligations.

The sureties argued that SWPC failed to perform its obligation to pay its share of the liquidated damages and, as a result, they were not required to pay. SWPC argued that another provision of the surety bond controlled, with this provision stating:

The court agreed with SWPC, finding that Dick had the obligation to pay liquidated damages to AES pending the dispute resolution procedures regarding apportionment.

The Significance of the Case

The Siemens Westinghouse case is significant from a variety of perspectives, particularly in that it shows how sophisticated parties develop their consortium agreement. The text quoted above shows that the parties obviously considered the issue of which of the two companies was to bear the initial responsibility for paying the owner liquidated damages. While the language could have been written a bit clearer, particularly if Dick believed at the time of contracting that its position was right, the most telling point was that it was virtually impossible to apportion responsibility for delay during contract performance.

What is the lesson smaller industry players can learn from Siemens Westinghouse about forming their design-build teams? You need to figure out which team member will be financially responsible to the owner and potentially "out-the-cash" pending full resolution of all issues. Do not be misled into thinking that this is just a financing issue and involves a temporary outlay of funds. It can be a huge factor in how the overall case will be resolved. The party who pays first has a strong incentive to get the case resolved quickly and may face pressure to settle on less than favorable terms.


Opinions expressed in Expert Commentary articles are those of the author and are not necessarily held by the author's employer or IRMI. Expert Commentary articles and other IRMI Online content do not purport to provide legal, accounting, or other professional advice or opinion. If such advice is needed, consult with your attorney, accountant, or other qualified adviser.

Home > Free Risk & Insurance Information > Expert Commentary > Legal Trends > Design-Build Liability > Design-Build Teammates—Who Pays Liquidated Damages First? (October 2004)