Unexpected Hazardous Materials—What Do You Do When the Owner Says "Keep Going"?

April 2005

Most of us know what is supposed to happen when a contractor encounters unexpected hazardous conditions at the site. You: (1) immediately stop work, (2) notify the owner, (3) wait for the owner to remediate the problem, and then (4) resume work when the owner says that the conditions are remediated. But what happens if there is a dispute over whether the materials are in fact hazardous or have been properly remediated? A recent design-build case gives us a sense of the challenges.

by Michael Loulakis
Wickwire Gavin, P.C.

Empire Energy Management Systems, Inc. v Secretary of the Air Force, 362 F3d 1343, 2004 U.S. App. LEXIS 5512 (Ct Appeals Federal Circuit 2004), involved the appeal of a Board of Contract Appeals decision holding that the government had properly default terminated the developer of a power generation plant. The government terminated the developer because the project failed to reach commercial operation within the time required by the contract. The developer argued that its delays were excused by hazardous materials encountered at the site. The appellate court affirmed the Board’s decision, finding that the developer’s claimed environmental concerns were not an excuse and that the delays were the fault of the developer.

Empire Energy Management Systems entered into a 25-year design-build-own-operate-maintain contract with the Air Force for a cogeneration facility that was to provide electricity, chilled water, hot water, and steam to MacDill Air Force Base (MacDill AFB). Payment to Empire was based on utility charges paid by the Air Force over the life of the contract. The contract allowed the Air Force to terminate Empire for default if commercial operation was not achieved on or before August 27, 1993, or if Empire failed to "make progress, so as to endanger performance of [the] contract." The contract required Empire to comply with all federal, state, and local environmental and archeological laws and regulations, and contained several standard contract clauses from the Federal Acquisition Regulations (FAR), including the standard FAR default clause.

EPA Involvement

Shortly after breaking ground in February 1991, Empire stopped work because of a dispute with its financer. On August 15, 1991, while the work was still stopped, the U.S. Environmental Protection Agency (EPA) designated MacDill AFB as a hazardous waste facility under the Resource Conservation and Recovery Act (RCRA) and issued a permit that required the Air Force to conduct a RCRA Facility Investigation (RFI) on several oil-water separator units, including one near the site of Empire’s power plant. The permit also required the Air Force to give notice to EPA as soon as possible of any planned physical alterations or additions to the permitted facility.

Although Empire resumed work on May 4, 1992, it was not made aware of the RFI until June 5, 1992. Prior to becoming aware of the RFI, Empire had discovered, on May 15, 1992, some oil-based contaminants near the oil-separator unit located on its site. As a result, it stopped work and requested a stop work order from the Air Force on the grounds that it had encountered "an unknown quantity of an environmentally hazardous substance on the project site."

The Air Force denied Empire’s request for a stop work order, but subsequently hired Dames & Moore, an environmental contractor, to investigate the soil conditions on Empire’s power plant site. On July 21, 1992, Dames & Moore began taking samples throughout the plant site and tested for organic vapors, and ultimately issued a report that the site complied with all applicable federal, state, and local environmental laws and regulations and that the site was suitable to complete construction of the power facility. This report was provided to Empire on August 28, 1992.

On September 3, 1992, Air Force officials met with an EPA representative and provided her with the Dames & Moore report. Citing this report, the representative wrote a letter on December 11, 1992, stating that the power generation site did not need to be subject to the RCRA Facility Investigation. The Air Force provided this letter to Empire on January 8, 1993, and directed Empire to return to work. Empire refused, still believing that there were environmental issues at the site.

The Air Force issued a cure notice to Empire on April 28, 1993, stating that Empire’s failure to perform work was placing it in jeopardy of missing its required completion dates. Empire responded to the cure notice on May 10, 1993, asserting that it had continued performance of the contract by continuing its investigation into the site’s "environmental status" and that "a fast track construction schedule would enable Empire to achieve commercial operation on or before August 27, 1993."

Empire resumed work on May 24, 1993, but it remained substantially behind schedule. Empire requested a schedule extension, which the Air Force refused. The Air Force terminated the contract for default on September 1, 1993, stating that Empire had failed to meet the contract’s termination date of August 27, 1993. Empire appealed this decision to the Board of Contract Appeals, and sought to recover its costs of more than $30 million.

Board of Contract Appeals

The Board found that the Air Force was not justified in terminating Empire because the August 27 completion date had passed, since the facts showed that Empire was entitled to 53 days of excusable delay. However, the Board nevertheless concluded that termination for default was proper given that Empire failed to make sufficient progress on the work.

After examining the facts, the Board found that Empire had only completed 28 percent of the work as of the termination, and needed 154 additional days to complete the project. Since there was "no reasonable likelihood Empire could have met [Commercial Operation] with a 53-day extension," the Board concluded that the Air Force had a reasonable basis for default termination of the contract on September 1, 1993.

The Board also rejected Empire’s claims that it had been justified in refusing to work on the site because of environmental concerns, believing that Empire could not have had, and did not in fact have, any reasonable environmental concerns that its action would create a material violation of environmental regulatory requirements. After considering the evidence, the Board found that "construction work could have been done on site without interfering with the RFI work" and that "construction could have proceeded without violating the permit." The Board stated:

  • There is no evidence of any remediation at or near the [power generation] site, no proof of actionable contamination and MacDill was never cited by EPA for violations of any kind at the [power generation] site…. Thus, we cannot find that the effluent from the [oil-water separator] contained actionable contamination, i.e., matter that violated the environmental laws and regulations of the United States or Florida.

It also concluded that Empire "was posturing when it stopped work" and that Empire was attempting to establish grounds for a claim.

U.S. Court of Appeals

Empire fared no better in its appeal to the U.S. Court of Appeals for the Federal Circuit. This court rejected Empire’s argument that it would have been "flatly unlawful" for Empire to have commenced work before the Air Force notified EPA of the construction activity and the EPA approved the work. If this were the case, then Empire would have been entitled to a time extension of at least 217 days, which would have protected it from a termination. However, the RCRA permit did not require EPA approval for any particular action by the Air Force—it only required that the Air Force notify EPA of planned physical alterations, which it had done on September 3, 1992. No legal authority was cited by Empire for the proposition that EPA approval was required under a RCRA permit.

Empire’s next argument was that even if EPA approval was not required under the permit, Empire could reasonably have insisted on it before beginning work, since the contract required Empire to comply with all federal laws and regulations. It claimed that possible environmental problems had been identified at the site, including potential contamination of the soil, and that it risked having environmental liability if it dispersed any contaminated soil during the course of grading and filling the construction site. Under these circumstances, Empire argued that it could reasonably insist on EPA approval before resuming work.

While the court agreed with Empire’s general views on possible environmental liability, it found that "the mere assertion of a colorable claim by the contractor (later found to be meritless) that its actions would violate some regulatory requirement does not excuse performance." The court found substantial evidence to support the Board’s findings that Empire’s environmental concerns were "pretextual" and "unsubstantiated," and that Empire was "posturing" to take advantage of the situation.

Empire next argued that "time was not of the essence" and that the Air Force could not have terminated the contract because of Empire's delays since the unique nature of this contract placed the risk of failure entirely upon the contractor and its lender. It also argued that the liquidated damages clause precluded a termination for default because of late completion. The court’s rejection of these arguments was not only based on the language of the contract, which specified that failure to meet commercial operation by August 27, 1993, was a "condition of default," but also prior caselaw giving the government the right to terminate for late completion even though the contract contained a liquidated damages provision.

The court quickly disposed of Empire’s argument that the Air Force had used an improper basis for terminating the contract:

  • Our decisions have consistently approved default terminations where the contracting officer’s ground for termination was not sustainable if there was another existing ground for a default termination, regardless of whether that ground was known to the contracting officer at the time of the termination.

Given this, the Board had the right to justify the termination on the "failure to make progress" language of the default clause if it reasonably concluded that Empire would be unable to complete the project by the proper completion date. Given the evidence, the appellate court agreed that there was no "reasonable likelihood" that a 53-day time extension would have enabled Empire to achieve commercial operation on time.

Conclusion

What are the lessons to be learned from this case? Perhaps the most important is that a contractor cannot simply sit back and raise unsubstantiated fears about a contamination problem. After the Dames & Moore report was issued, Empire did not appear to have a basis for arguing that the work should remain suspended. If it reasonably believed there was a problem, then perhaps it should have retained its own experts, demanded indemnification, or taken similar measures that would have placed the burden of the "next move" on the Air Force. Both the Federal Appeals Court and the Board made it appear that Empire was playing games, and that it had other reasons for stopping the work.


Opinions expressed in Expert Commentary articles are those of the author and are not necessarily held by the author’s employer or IRMI. This article does not purport to provide legal, accounting, or other professional advice or opinion. If such advice is needed, consult with your attorney, accountant, or other qualified adviser.