"What Performance Did the Parties Bargain For?"

January 2005

The California Supreme Court just issued its opinion in a case of both interest and consternation to the surety industry and the construction industry, alike. In Lewis Jorge Construction Management, Inc. v Pomona Unified School District, Docket No. S112624, the court ruled that a contractor cannot recover lost profits suffered on unidentified future construction contracts as a result of impairment to its bonding capacity, which, in turn, resulted from a project owner's wrongful default termination of the contractor.

by Marilyn Klinger
Sedgwick, Detert, Moran & Arnold LLP

The facts of the case are standard. Lewis Jorge was a public works contractor with a $10 million dollar per project bonding limit and an aggregate limit of $30 million. It entered into a $6 million contract with the Pomona Unified School District. Once the project became 6 months behind schedule, the District terminated Lewis Jorge and demanded that the contractor's surety complete the project. The surety responded affirmatively and arranged for a completion contractor to complete the project.

Although not set forth in the opinion, that surety appears to have ceased issuing surety bonds for Lewis Jorge. The court did note that, by mid-1997, "the only sureties willing to provide Lewis Jorge with bonding imposed a limit of $5 million per project, with an aggregate limit of $15 million…." In 1998, Lewis Jorge ceased operations.

Lewis Jorge successfully sued the District for breach of contract, among other theories, based on its assertion that the default termination was improper. During trial, Lewis Jorge presented evidence of its lost profits from the District's breach of contract, based on its profitability for the 4 years prior. Its lost profits experts provided testimony that Lewis Jorge's gross revenues would have been $95 million, that its average profit was 6 percent, such that its lost profit was $4.5 million, reduced to present value of $3,148,107. The jury awarded Lewis Jorge $362,671 on the contract breach and $3,148,197 for lost profits resulting from "the loss or reduction of its bonding capacity."

Legal Analysis

In issuing its ruling, the court first noted the overall rule regarding contract damages—such damages seek to approximate the agreed-upon performance and, therefore, cannot exceed what the injured party would have received if the parties had properly performed the contract. In that way, the parties are able to estimate, in advance, the financial risk of the transaction.

Then the court considered whether lost profit damages arising from a diminution or elimination of bonding capacity were recoverable under either of two types of contract damages: (1) general (direct) damages or (2) special (consequential) damages.

General (Direct) Damages

The court explained that general damages are those that flow directly and necessarily from the breach of contract, that is, in the ordinary course would likely result from the breach. Thus, general damages are those that were within the contemplation of the parties because their occurrence was predictable. Put another way, general damages provide the nonbreaching party with the benefit of its bargain.

The lower court allowed the lost profit damages as general damages finding that impaired bonding capacity for public works contractors has long been recognized as a direct consequence of a public owner's breach of its contract. Therefore, the District should have known that such would reduce Lewis Jorge's ability to obtain bonds and, correspondingly, its ability to win construction contracts. However, the court noted that, for general damages, the trial court should have evaluated what performance the parties bargained for, noting that general damages are based on the value of the performance itself, not the value of the consequence of lack of performance. Thus, unearned profits directly flowing from the breached contract are allowed general damages. Unearned profits flowing from the inability to perform a collateral, derivative, or related contract to the one breached have also been allowed.

As to damages in the form of lost profits on future unidentified construction projects, the court noted that no court in California or outside of California, for that matter, has allowed such damages against a breaching construction owner except for one 30-year-old Montana action that has not been followed, even in Montana.

The court distinguished Arntz Contracting Co. v St. Paul Fire & Marine Ins. Co., 47 Cal App 4th 464, 489 (1996), which allowed Arntz to recover lost future profits on unidentified construction contracts against Arntz's former surety. It noted that, in that case, the contractor's recovery of lost profits on future contracts was not based on the fact that its bonding capacity was impaired but from the surety's reneging on its commitment of future bonding. As the court stated with respect to Arntz:

  • Because the contract was one for future bonding, it was entirely within the contemplation of the surety that its breach of the contract—resulting in the contractor's loss of actual bonding—would preclude the contractor from bidding on and being awarded major projects.

In concluding that Lewis Jorge was not entitled to its lost future profits, it concluded that Lewis Jorge was only entitled to full performance on the breached contract, which included profit on that contract limited by the contract price and the cost of performance. As the court put it, "What performance did the parties bargain for?" "[W]e cannot say that the parties' bargain included Lewis Jorge's potential profits on future construction projects it had not bid on and been awarded."

Special (Consequential) Damages

The court noted that special or consequential damages do not arise directly and inevitably from a breach of the contract. Rather, they are secondary and derivative losses arising from the circumstances that are particular to the contract or the parties. Accordingly, special damages can only be recovered if the breaching party knew or should have known of those circumstances. Because the breaching party knew or should have known of those circumstances, the resulting damages meet the test of foreseeability—they were not unanticipated damages or those beyond the expectation of the parties.

The court noted that Lewis Jorge did not establish that, when the contract was formed, the District contemplated that a breach would lead to the impairment of Lewis Jorge's bonding capacity and, thus, its ability to obtain future contracts. The court noted that even Lewis Jorge's bonding agent believed the surety's cutback was only temporary. The court noted that the trial evidence indicated that the breach could or could not have impaired Lewis Jorge's bonding capacity. The District testified that it did not know Lewis Jorge's financial status or the criteria that its surety used to determine bonding credit. Accordingly, an impairment in its bonding capacity or the profits that Lewis Jorge might lose on potential future projects were not foreseen or reasonably foreseeable.

As an aside, the court acknowledged that there are a few courts that have accepted the concept that a party may recover lost profits on unrelated future contracts but, typically, in those cases, the courts did not actually award those damages because they found them to be too speculative, conjectural, and remote or because their occurrence was uncertain.

Conclusion

In conclusion, the court stated:

It is indisputable that the District's termination of the … contract was the first event in a series of misfortunes that culminated in Lewis Jorge's closing down its construction business. Such disastrous consequences, however, are not the natural and necessary result of the breach of every construction contract involving bonding. Therefore, lost profits are not general damages here. Nor were they actually foreseen or foreseeable as reasonably probable to result from the District's breach. Thus, they are not special damages in this case.


Opinions expressed in Expert Commentary articles are those of the author and are not necessarily held by the author’s employer or IRMI. This article does not purport to provide legal, accounting, or other professional advice or opinion. If such advice is needed, consult with your attorney, accountant, or other qualified adviser.